Reasons for Manston delay made public

Details have now been made public regarding the temporary withdrawal of a development consent order (DCO) application to develop a cargo hub at Manston Airport, located in the south-eastern corner of the UK.

The application by developer RiverOak Strategic Partners (RSP), submitted on April 10, included plans for 12,000 air cargo flights per year through the airport.

Detail has now been provided by the government’s Planning Inspectorate, as to why the approvals process has temporarily stalled.

The inspectorate confirmed that it called the applicant’s legal representatives (BDB Law) on May 1, setting out its principal concerns in respect of the application documents. Those concerns included, it said:

• An absence of sufficient information within the application documents upon which the Planning Inspectorate could base a decision about whether the proposed development constitutes a Nationally Significant Infrastructure Project (NSIP) within the meaning of the Planning Act 2008.

• Gaps in the ecological, archaeological and ground investigation survey data presented within the Environmental Statement (ES) accompanying the application, which create uncertainty in the assessment of likely significant effects.

• Inconsistencies/omissions in the noise and vibration assessment.

• The adequacy of the Transport Assessment accompanying the ES.

• The adequacy of the Funding Statement.

On May 3 a teleconference was held between the Planning Inspectorate, BDB Law and RSP. During this teleconference the Planning Inspectorate repeated its principal concerns to RSP, which then confirmed its intention to withdraw the application.

Subsequently, the application was formally withdrawn as per a letter of May 4.

Then, on May 11, a meeting took place between the Planning Inspectorate and the applicant at which the Planning Inspectorate provided more detailed advice in respect of the concerns noted above.

Any resubmission by RSP will be treated as a new application for the purposes of the approvals process. The Planning Inspectorate will then have up to 28 days to take a decision on whether the application will be accepted for examination.

Share this story

Related Topics

Latest cargo airport news

Yusen Logistics takes operations to Ezhou Huahu Airport

Japanese firm Yusen Logistics plans to start cargo terminal and charter operations at Ezhou Huahu Airport in China next year….

Read More

Share this story

Emirates gets ready for SAF at Schiphol

Emirates has commenced the activation of its sustainable aviation fuel (SAF) agreement with Neste at Amsterdam Schiphol Airport. Over 2m…

Read More

Share this story

FedEx expands Shenzhen airport facility

FedEx Express has upgraded its Shenzhen Baoan International Airport gateway facility in Shenzhen, China by renovating and expanding the import…

Read More

Share this story

Air Cargo News

Air Cargo News
Established in 1983, Air Cargo News is the leading source of news, information, interviews, analyses and reports to the global airfreight industry. Our leading portfolio includes print, digital and events that give businesses in the airfreight industry the ability to connect with decision-makers in this sector.