VIDEO: Shannon’s new runway, ta Mac for a great job

The rehabilitation of Ireland’s longest runway, at Shannon Airport, is proving a triumph of logistics as the equivalent of one football pitch is re-laid between dusk and dawn each night, the airport has revealed.
Shortly before midnight, following the last arrival/departure at Shannon, a team of 90 vehicles and 70 people roll in for over four hours work on the 3,200 m runway – among the longest runways in Europe.
By the time they finish and get ready for a ninety minute health and safety inspection – before early morning flights resume – the team will have laid enough asphalt to cover an entire football pitch.

The work started in April and by the time it finishes in October 2017, some 50,000 tonnes of asphalt will be laid – equating to 72 football pitches.
Speaking half way through the works, Shannon Airport operations director Niall Maloney explained:  “It’s quite a complex job because not alone is there a huge volume of work being done but there’s a huge focus on the clock and, particularly, on safety.
"The runway must be open and operational every morning for our first transatlantic customers before six am. To ensure this happens our own dedicated Shannon Airport project team, working with our contractor, take 90 minutes to run all the necessary safety checks before that can happen.
“It’s a well-rehearsed activity by our contractor, Lagan Asphalt. A chain of vehicles arrive on site as soon as the last flight is processed.  Planers, tarmacadam trucks, empty lorries, rollers – up to 70 vehicles roll onto the runway for the works every night.  By the time we are finished in October we will have a brand new surface that will serve the airport and the region for the next 25 years.”
Said Shannon Airport managing director Andrew Murphy:  “The project is part of an overall €20m+ programme here at Shannon Airport that is focused on works at the terminal building itself to the runway."
The airport’s runway, built in 1961, was last fully rehabilitated in 1983 and has under gone regular maintenance over the intervening years. The current work includes resurface and rehabilitation enhancements to Runway 06/24, including replacement of existing runway lighting and fittings, raising of the drainage channel, reinstatement of the airfield markings associated ducting and other minor site works. 

Share this story

Related Topics

Latest cargo airport news

Threat to cargo operations from strike action at Heathrow

Aircraft refuelling handlers working for AFS at London Heathrow Airport (LHR) will initiate industrial action for 72 hours beginning on…

Read More

Share this story

IAI joins STK and Incheon for 777P2F facility construction launch

Israel Aerospace Industries (IAI), Sharp Technics K (STK) and Incheon International Airport have laid the foundation for a Boeing 777…

Read More

Share this story

Emirates SkyCargo warns of backlogs following Dubai flash floods

Emirates SkyCargo is warning customers to expect delays as it continues to battle backlogs following flash flooding earlier in the…

Read More

Share this story

Air Cargo News

Air Cargo News
Established in 1983, Air Cargo News is the leading source of news, information, interviews, analyses and reports to the global airfreight industry. Our leading portfolio includes print, digital and events that give businesses in the airfreight industry the ability to connect with decision-makers in this sector.